UCAN files protest before CPUC against application of SDG&E for expedited approval of the Miramar Energy Facility II Project
Date of Filing/Decision
Application of San Diego Gas & Electric
Company (U 902 E) for Expedited
Approval of the Miramar Energy
Facility II Project
(Filed June 16, 2008)
UTILITY CONSUMERS ACTION NETWORK (UCAN)
INTRODUCTION
Utility Consumers' Action Network (UCAN) hereby protests SDG&E's application and,
specifically, its request for expedited approval of construction of a Miramar Peaking Plant.
UCAN's protest is based upon the following point:
* SDG&E has failed to show cost-effectiveness of the project. It also hasn't explained why
SDG&E customers should be charged for a project that is needed only because Calpine
has failed to honor its contractual obligations.
* SDG&E has failed to show that the project is, in fact, needed by 2009.
* SDG&E doesn't address the fact that even if Miramar 2 is needed in 2009, that it won't
likely be used again in 2016, at the earliest.
* SDG&E does not explain why it waited over 45 days before filing this application.
These issues will be discussed in greater depth below. Based upon these factors,
UCAN urges the Commission to reject SDG&E's application unless SDG&E can offer detailed
responses to the questions posed by UCAN below.
UCAN shares SDG&E's concerns about the reliability of electric generation during the
summer of 2009. The purpose of the contract that SDG&E entered into with Calpine to build
the Otay Mesa project was, in part, to ensure the availability of power during the summer of
2009. The failure of Calpine to honor its contractual commitment now appears to imperil San
Diego customers and, at a minimum, impose a fairly expensive generation resource that will
likely be rarely used after 2009.
For the reasons stated below, UCAN protests the application submitted by SDG&E,
although not the expedited processing of the application. In considering the application, UCAN
urges the Commission to consider the following additional matters:
Resource Needs: If the CPUC is to conduct an evidentiary process in support of this
application, UCAN is prepared to show that Miramar 2 is not needed in any year before 2010 if
the deployment of AMI is accelerated. If SDG&E is unable/unwilling to so accelerate AMI, then
Miramar 2 may be needed in 2009. However, once Calpine's Otay Mesa station comes on-line in the fall of 2009 (and in any case, before the summer of 2010), SDG&E would no longer need Miramar 2 until 2016. UCAN is prepared to demonstrate that SDG&E has ample surpluses in 2010-2012 (due to 370+ Mw of AMI and demand response such that even if South Bay were to be retired in its entirety prior to the summer of 2010, SDG&E would still have sufficient power to address its needs without Miramar 2.
Second, adding Carlsbad, as proposed by NRG, provides 222 Mw more of net capacity resulting in surplus capacity in 2013-2015, inclusive. With the proposed NRG plant, the first year in which new CTs have to be added is 2016. As will be discussed below, an evidentiary process may not be necessary to establish these facts.
If the Commission reviews the assumptions adopted by the Assigned Commissioner/ALJ in their June 20, 2008 ruling (see Appendix to that ruling) it will find that Miramar 2 is not needed in any year before 2010. And, even if needed in 2009, once Otay Mesa comes on line in the fall of 2009 (and in any case, before the summer of 2010), then SDG&E wouldn't need Miramar 2 until 2016 with the assumptions contained in the June 20th ruling.
Costs. SDG&E admits in its application that Calpine's Otay Mesa generation station
construction is behind schedule, with the new on-line date in the fall of 2009. If not for this delay,
UCAN submits that Miramar 2 would not be required by 2009 and, possibly, not at all. SDG&E
appears to want to impose 100% of the $56+ million price tag for Miramar 2 upon SDG&E's
customers, even though it would not have been necessary to build the plant until 2016 absent
Calpine's failure to honor its contract. Moreover, SDG&E's estimate doesn't address the natural
gas costs to operate the peaker - costs that might have been lower had Otay Mesa been
operational. The Commission will need to review the confidential Calpine/SDG&E contract to
determine how the contract addresses liquidated damages and whether SDG&E anticipated the
need for power in Summer 2009 in that contract.
The Commission also needs to ensure that the cost of the proposed plant is reasonable.
This can be done by comparing its cost to reasonable CT costs represented by SDG&E in the
Sunrise Powerlink case. In Sunrise, (Phase 2) SDG&E asserted that 140 Mw of CTs in 2010
(Ex. SD-142, p. 3) would have a levelized cost, transmission included of $26.1 million per year
(Ex. SD-143, p. 20, sum of $24.3 million/year for 2010 CTs and $1.8 million/year for
transmission), or $26,100/140 = $186/kw-year. Discounting by 8.4% per year to 2008 terms (as
per SDG&E's Miramar 2 testimony, p. 28) yields $186/1.084/1.084 = $158/kw-year. The
Commission must compare that cost to the confidential Miramar 2 cost in $/lw in Table 4 on p.
28 of its Miramar 2 testimony.
Expedited processing the application: SDG&E claims that it needs a decision in no more
than 80 days. In order to process this application in a timely fashion, the CPUC will need to
know:
-
If SDG&E was informed on May 1, 2008 that Otay Mesa was slipping off schedule why
did it wait until June 16th to file its application? It isn't clear why SDG&E's testimony
doesn't include a letter from Otay Mesa dated May 1st confirming its breach of terms. It
also isn't clear from its application why SDG&E didn't file the Miramar 2 CPCN earlier
than June 16th, given that it admits that it would need to be approved by September
2008 to be on-line by July of 2009. -
What arrangement has SDG&E made to have Calpine defray some of the costs of
Miramar 2 due to its failure to deliver its Otay Mesa plant on a timely basis? -
What steps did SDG&E take to offer premiums to other CT developers to accelerate
deployment of their projects? -
Why did SDG&E never publicly announce that it had signed contracts in 2007 with
Wellhead and GE for the turbine and the EPC portions of Miramar 2 given that this
information might have made it possible for other plant developers to expedite
processing of their proposals? -
How do the costs of maintaining South Bay in operation past 2010 compare to the costs
of building and maintaining the Miramar 2 plant? -
Is the proposed $56 million cost of the project is reasonable compared to costs
established in the Sunrise proceeding.
Need for evidentiary hearings. Given the timeline dictated by SDG&E, it does not seem
possible to hold evidentiary hearings to test the veracity of the assertions offered in SDG&E's
application. However, it may not be necessary. The Commission has available to it an
extensive evidentiary record from the Sunrise Powerlink application (A. 06-08-010) that includes
most of the facts asserted by SDG&E in its application and testimony. UCAN submits that the
evidentiary record in the Sunrise case addresses many of the important factual questions, such
as the need for and cost of Miramar 2. If SDG&E provides prompt and satisfactory responses
to the other questions posed by UCAN above, then the application may be sufficiently supported
so as to avoid the need for evidentiary hearings. The burden will fall upon Energy Division and
the assigned ALJ to apply the Sunrise evidentiary record to this application.
/s/
Michael Shames, Esq.
On behalf of UCAN
3100 Fifth Ave. Suite B
San Diego, CA 92103
Phone: 619-696-6966
Fax: 619-696-7477
Email: mshames@ucan.org
I hereby certify that I, Laura Impastato, have this day served a copy of the foregoing
PROTEST OF UTILITY CONSUMERS' ACTION NETWORK on the electronic service list
below that includes the applicant and the assigned Commissioner(s) and Administrative Law
Judge(s). Dated at San Diego, California, this 7th day of July, 2008.
Signed,
/s/
Laura Impastato
wkeilani@semprautilities.com
jpacheco@sempra.com
liddell@energyattorney.com
mrw@mrwassoc.com
ddavie@wellhead.com
cab@cpuc.ca.gov
| Attachment | Size |
|---|---|
| Miramar2protest.pdf | 97.74 KB |
Like what you see? Go ahead and show your support! UCAN is a truly independent non-profit watchdog organization, dependent on grassroots donations like yours!
Utility Consumers' Action Network - (619) 696-6966
Terms and Conditions
UCAN.org is made available by the Utility Consumers' Action Network to assist you in becoming what you always knew you could be: a consumer ROCK STAR! We take no corporate money, and are beholden only to you, the consumer. As such, the site is here for educational, advocacy, and empowerment purposes, as well to to give you general information and a general understanding of the law. Just remember this site is NOT here to provide specific legal advice. By using this web site you of course understand that there is no attorney-client relationship between you and the Web Site publisher, UCAN. The Web Site should not be used as a substitute for competent legal advice from a licensed professional attorney in your state.
That said, get to digging on the site, inform yourself, speak your mind, and earn Watchdog Bones! This is YOUR site, and we mean it. So comment on any of the content, discuss the latest issues in the forums, file a complaint on a company with the Fraud Squad, and generally cut loose.
See our Terms of Use, Privacy, and Copyright complaint policies as well as our Content Reuse Policy, Some Rights Reserved. Remember, if you have any questions about copyright law or need legal information regarding intellectual property, the internet, or new technologies, visit our affiliate New Media Rights at www.newmediarights.org. If you are in the San Diego region, you can also can apply to use New Media Rights' multimedia studio and equipment for free.








Post new comment